Most air source heat pump installations take two to five days on site. A straightforward swap in a typical three-bed home sits at the shorter end, while jobs involving several new radiators or awkward pipe runs stretch towards a week. You’ll usually be without heating and hot water for one working day in the middle, not the whole job.

That’s the on-site answer. The full journey from first enquiry to warm radiators is more like four to eight weeks, and it’s worth understanding both timelines so nothing surprises you.

What happens before installation day?

The install itself is the short part. Before anyone turns up with a heat pump, a few things need to happen.

First comes the heat loss survey, where we measure every room and calculate exactly what your home needs. Allow a couple of hours for the visit and expect your quote and system design shortly after.

Then there’s the paperwork you never see. Your electricity network operator has to approve the connection, which can take a couple of weeks depending on the network. If you’re claiming the £7,500 Boiler Upgrade Scheme grant, the voucher application runs in parallel, and the noise assessment for planning compliance gets done at the design stage. A good installer handles all of this and simply tells you when your start date is.

So while the van is only outside for a few days, plan for four to eight weeks between saying yes and the system going live. If your boiler has just died in January, tell your installer, because most can prioritise and some will fit temporary heating in the meantime.

What does the installation itself look like, day by day?

Every job is different, but a typical three to four day installation runs roughly like this.

Day one is groundwork and positioning. The outdoor unit goes onto its base or brackets, and the team starts running pipework between the unit and wherever your hot water cylinder is going. Your existing heating usually stays on tonight.

Day two is the switchover, and it’s the disruptive one. The old boiler comes out, the cylinder goes in, and the new pipework gets connected up. This is the day you’re without heating and hot water, so we always warn customers in advance. Kettles still work.

Day three is radiators, electrics and commissioning. Any radiators being upgraded are swapped, the electrical connections are completed, the system is filled, pressure tested and fired up for the first time.

Day four, where needed, is fine tuning and handover. The system gets balanced, the controls are set up properly, and we walk you through how to run it, which matters more with a heat pump than a boiler because the habits are different.

What can make it take longer?

A few honest additions to watch for. If most of your radiators need upsizing, add a day or two. If there’s no obvious home for the hot water cylinder and one needs creating, likewise. Older properties with awkward pipe runs, microbore pipework that needs replacing, or a consumer unit that needs upgrading before the electrics can be connected all add time, and all of them should be identified at the survey stage rather than discovered mid-job.

That’s the real point of this article. The difference between a smooth three day install and a messy ten day one is almost never the heat pump. It’s whether the survey was thorough enough to find the complications before the job started.

How disruptive is it really?

Less than a kitchen, more than a boiler swap. You’ll have people in the house for the duration, some lifted floorboards or trunking depending on pipe routes, and that one day without heating and hot water. Most customers tell us the anticipation was worse than the reality, and you don’t need to move out or take the whole week off work.